by Dev_NCPAdmin | Jul 10, 2024 | Uncategorized
The Challenge: NCP undertook a challenging project to refurbish critical equipment. We focused on three 32’Ø x 15′, 7400kW SAG mills. Two mills required refurbishing multiple components, while the rest were allocated to specialized fabricators worldwide....
by Dev_NCPAdmin | Jul 10, 2024 | Uncategorized
The Challenge: The KCC client faced a critical challenge: the need to enhance their plant’s throughput. Previous attempts at refurbishing the existing 32ft mill shells and heads on-site had failed. These efforts involved welding up worn-out areas and cutting out...
by Dev_NCPAdmin | Jul 10, 2024 | Uncategorized
The Challenge: Original OEM under designed the gear and pinion set and approached NCP to review and investigate why the girth gear was failing within a very short period of time. The Solutions: NCP gathered the necessary technical detail from measurements of...