Metorex
- Ruashi mine Complete Comminution Circuit NCP were awarded
the contract to design and supply the complete communition
circuit to the Ruashi plant in the DRC. The front end
with feed the new EW plant at Ruashi. The design of the
plant enables constant feed to the existing 20ft diameter
SAG mill at 200tph and 100tph feed to the new 1500kW ball
mill supplied by NCP. The contract includes supply and
installation of a primary crushing station including a
42x48in STRB Jaw Crusher. The crushed material is deposited
onto a 450tph stockpile, which feeds material th4rough
two Armco tunnels at controlled rated to the two mills.
The
contract includes all civil layouts, structural design,
design and supply of all mechanical equipment, design
and supply of all electrical and instrumentation. NCP
will partner with G5Projects for the installation portion
of the contract. The switchgear portion of the contract
includes 15kV MV switchgear design and supply, a new 5MVa
transformer, 2200V switchgear and all MCCs. NCP will issue
control narratives to TMP for the plant SCADA design.
NCP have also been awarded the spares contract for the
complete ROM feed prep area.